A new study puts hard numbers on the power behind the cloud and AI boom. Researchers at the Harvard T.H. Chan School of Public Health estimate that 403 hyperscale data centers in the US used between 68 and 99 terawatt-hours of electricity from May 2024 to April 2025.

That is about 1.8 percent of all US electricity. The study, published in Nature Sustainability, links that use to about 25.7 million metric tons of carbon dioxide, two to three times higher than an earlier estimate from 2018.

Fossil fuels supplied about 54 percent of the power, with natural gas around 38 percent and coal around 15 percent. Four states, Virginia, Oregon, Ohio and Iowa, account for more than half of the load.

The team built its own list of facilities from satellite images rather than relying on company disclosures, which are often partial.

Why it matters for infrastructure planners: the grid mix where a data center sits shapes its footprint as much as its efficiency does. As AI demand grows, expect more pressure on operators to show where their power comes from, and on regulators in Virginia and the Midwest to plan for new load.